Rooppur Sends 350 MW to the National Grid for the First Time as Trial Supply Begins
Electricity produced at Rooppur, Bangladesh's first nuclear power plant, has been connected to the national grid on a trial basis for the first time. The supply began after a series of technical activities and complex tests in various stages.
On Tuesday (November 17) at 3 pm, in the presence of Science and Technology Minister Fakir Mahbub Anam, supply of 350 megawatts of electricity from the first unit to the national grid began for the first time.
Under the set plan, under the initial trial connection, the electricity produced will be supplied to the national grid for about 8 to 10 hours.
During this time, important technical tests will be completed, including observing the effectiveness and stability of the plant's turbine, generator and coordinated operating system with the grid.
Later, the plant will be disconnected from the national grid for various technical tests. After a break of about 28 hours, it will be reconnected to the grid for 4 to 6 hours to complete the plant's necessary technical and operational tests.
At every stage of testing, the performance of the plant's various systems, the performance of the turbine and generator, and coordination with the national grid will be closely checked.
If the results of all technical tests are satisfactory and all scheduled work of this stage is completed, approval from the Bangladesh Atomic Energy Regulatory Authority (BAERA) will be required for the next trial operation. Subject to BAERA's approval, the plant will again be connected to the national grid on a trial basis and taken forward to the next stage of electricity supply.
Under the agreement with the Russian contractor, once the 10-month trial operation is completed, electricity will be supplied commercially from the first unit at full capacity on a permanent basis. Through this, the first unit will be handed over (provisional takeover) from the Russian contractor to the Bangladesh Atomic Energy Commission.
Later, through a government gazette notification, NPCBL's work as the operating organisation will begin.
Each of the Rooppur nuclear power plant's two units has a production capacity of 1,200 megawatts. The plant, with a total capacity of 2,400 megawatts, is expected to make an important contribution to meeting the country's growing electricity demand, ensuring energy security and producing sustainable electricity.
The Rooppur nuclear power plant's trial grid connection is a historic step in the progress of Bangladesh's power and energy sector. Through it, Bangladesh has moved another step forward in nuclear technology-based electricity generation.