Rooppur nuclear power reaches national grid for the first time, 350 MW trial supply begins
Ending a long wait, the Rooppur Nuclear Power Plant has touched a historic milestone in the country's power and energy sector. On Tuesday (17 November) at 3:16 pm, trial supply of 350 megawatts of nuclear power from the plant's first unit to the national grid began.
With this, the process of supplying power from the plant's first unit to the national grid on a trial basis has started. However, the plant is not going into commercial production right now.
The grid connection programme began in the presence of Science and Technology Minister Fakir Mahbub Anam. Also present were Science and Technology Secretary Md Anwar Hossain, Bangladesh Atomic Energy Commission Chairman (in-charge) Dr M Moinul Islam, Bangladesh Atomic Energy Regulatory Authority (BAERA) Chairman Mahmudul Hasan, Nuclear Power Plant Company Bangladesh Limited (NPCBL) Managing Director Dr Zahedul Hasan, Project Director Dr Md Kabir Hossain, and engineers, scientists and officials concerned.
The Rooppur Nuclear Power Plant construction project confirmed the development in an immediate press release. It said that under the initial trial connection, the generated power will be supplied to the national grid for about eight to 10 hours.
During this time, important technical tests will be carried out, including observing the effectiveness and stability of the plant's turbine, generator and coordinated operating system with the grid. The plant will then be disconnected from the national grid for various technical tests. After a break of about 28 hours, it will be reconnected to the grid for four to six hours to complete the necessary technical and operational tests.
Plant officials say trial production may continue for several months after the start. With power reaching the grid, Bangladesh has become the world's 33rd country producing nuclear power, although formal recognition will come after full supply begins following the tests.
Rooppur plant sources say the trial phase of gradually increasing generation capacity has begun following the guidelines and standards of the International Atomic Energy Agency. Now, following design and regulatory conditions, about 350 megawatts of power will be supplied to the national grid from the first unit for a few hours.
After the start of supply, the performance of the nuclear reactor vessel, turbine, generator and several other pieces of equipment and automatic control systems will be tested. For these tests, the first unit will be temporarily shut down at different times and power generation and supply will be reduced or increased. However, customers will be able to use the power supplied to the grid throughout this period.
Plant sources say it will not be possible to ensure uninterrupted and stable power supply to the national grid during the trial phase. PGCB, the grid operating company, will take necessary measures to maintain the balance of the national grid in line with the temporary shutdown of the first unit and fluctuations in power supply. Officials of the Power Development Board (PDB) will also monitor the supply situation.
To gradually raise generation capacity to 100 percent, the necessary licence and approval must be obtained from the Bangladesh Atomic Energy Regulatory Authority (BAERA). Therefore, after the tests, the Rooppur authorities will submit a report of the results to BAERA. Capacity increase activities will begin after their approval, while trial supply to the grid will continue at the same time. It may take several months to gradually raise generation capacity to 100 percent. According to the contract with the Russian contractor, after 10 months of trial operation are completed, commercial power supply from the first unit will begin permanently at full capacity.
Earlier, in October 2023, the Rooppur plant was recognised as a nuclear facility after nuclear fuel arrived at the project area. With the receipt of the fuel, Bangladesh's name was added to the list of countries possessing nuclear energy.
The Rooppur Nuclear Power Plant is the largest single project in the country's history. The project is being implemented by the Atomic Energy Commission under the Ministry of Science and Technology. Operations are being carried out by a government company named Nuclear Power Plant Company Bangladesh Limited (NPCBL) under the commission. Russia's contractor Atomstroyexport is building two units of 1,200 megawatts each at Rooppur.
The Rooppur project deadline was until December 2025. The deadline has been extended in two phases to June 2028. According to the contract with the contractor, there is no scope to increase the project cost despite the extension of time. But due to the rise in the price of the dollar, the project cost has increased by Tk 26,000 crore. In total, the Rooppur power plant will cost Tk 138,686 crore.