Final nuclear fuel shipment reaches Rooppur as second phase of test power supply to the grid continues
The ninth and final shipment of uranium imported from Russia for the Rooppur plant, the country's first nuclear power plant, has reached the project area. With this, the process of importing the nuclear fuel designated for the plant's two units has been completed.
At 5:48 am on Friday (27 November), three specialised lorries carrying the uranium entered the Rooppur project area. The lorries were taken into the project under strict security provided by other law-enforcement agencies under the supervision of the army.
Project sources said nuclear fuel for the two units was brought in a total of nine shipments. Of these, two shipments were designated for additional fuel for the first unit and seven shipments for the second unit.
According to the plan of Rosatom, Russia's state nuclear agency, 163 uranium assemblies were to be brought in seven cargo planes for the second unit, and a further 48 assemblies in two cargo planes to refuel the first unit. With the arrival of the final shipment, the scheduled import programme has been completed.
Built with Russian technology, the Rooppur nuclear power plant has two VVER-1200 model units. Each unit has a power generation capacity of 1,200 megawatts. When both units are running at full capacity, a total of 2,400 megawatts of electricity can be added to the national grid.
Alongside the arrival of the final nuclear fuel shipment, test power generation and supply from the plant's first unit is also under way. At 10:20 am on 23 November, power supply to the national grid began for the second time.
At this stage, there is a plan to run tests by supplying 300 to 350 megawatts of electricity for 10 to 24 hours. Earlier, at 3:16 pm on 17 November, Rooppur's first unit was connected to the national grid for the first time.
That day, after generating power continuously for more than eight and a half hours, generation was temporarily stopped at 11:50 pm. In the first phase of testing, a maximum of 375 megawatts of electricity was generated.
Science and Technology Minister Fakir Mahbub Anam said that through the successful test, Bangladesh has emerged as the world's 33rd nuclear power country, and that it is joyful news for the whole nation. He said that after a long wait, continuous technical work and complex tests at various stages, electricity generated at Rooppur has been connected to the national grid on a trial basis.
Project Director Dr. Md. Kabir Hossain said the second phase of test power supply began at 10:20 am on 23 November. At this stage, 300 to 350 megawatts of electricity will be supplied to the national grid for 10 to 24 hours to test various aspects of the operation.
Under the contract signed with the Russian contractor, after 10 months of trial operation, commercial power supply at full capacity will begin in phases from the first unit. At that time, the Bangladesh Atomic Energy Commission will take over responsibility for the first unit from the Russian contractor through a provisional takeover.
Later, through a notification in the government gazette, the Nuclear Power Plant Company Bangladesh Limited (NPCBL) will begin operating as the plant's operating organisation.
After a long construction process, nuclear fuel imports and technical tests at various stages, the Rooppur nuclear power plant is moving towards preparation for full-scale production.