Belgium Orders Google to Halt Datacentre Construction Over Lack of Permits

Belgian authorities have ordered Google to halt construction work on a large datacentre in the south of the country. According to the authorities, Google's requests to modify the original terms of its planning permission did not have approval.
Raphaël Stokis, a Wallonia regional official, told the public broadcaster RTBF that inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused.
Stokis said the 300 workers had been given a verbal order to stop work, and that the order had been confirmed in writing to Google. Google said in a statement that it was committed to maintaining an open and collaborative dialogue with the regional authorities.
Google applied in 2025 to change its plans, including a switch from air cooling to water cooling. Local authorities initially approved the application but later revoked it after protests. Google has appealed, and a ruling is due early next year.
The building occupies about 3 hectares of a 50-hectare business park on the site of a former coalmine at Aiseau-Presles, about 15 kilometres west of Charleroi. It is one of three datacentres Google originally planned on the site.
Nicolas Yernaux, a regional government spokesperson, told Agence France-Presse that a report was being submitted to public prosecutors alleging a major offence: the illegal construction of a building covering 3 hectares.
The environmental group Greenpeace earlier this week published a report including drone footage that showed Google was carrying on construction work at the site despite lacking the correct permits. Greenpeace said the tech giant was continuing work even though in August the latest version of its planning permission was revoked, and added that it had filed an emergency appeal with local planning authorities.
Greenpeace said the climate crisis would only intensify in the region, and that against this backdrop the construction of energy-guzzling behemoths could not be allowed to go unnoticed.
Google's 2024 permit was to construct three smaller air-cooled datacentres, but in 2025 it applied instead to merge two of them into one much larger facility and switch to liquid cooling by drawing 600 cubic metres of water an hour from the nearby Sambre River.
The regional administration initially approved the amendments in April, but residents and protest groups appealed, and in August the Wallonia infrastructure minister, François Desquesnes, revoked the modified permit over drought concerns.
Google appealed against that decision to Belgium's council of state, and a ruling in the case is expected on 7 January. The legal row is the latest confronting the company in Europe as large tech companies push to build datacentres to support the AI boom.
In October, Finland opened a criminal investigation into possible breaches of environmental laws at a planned Google datacentre in the rural north of the country. Work there has been halted until environmental impact assessments are completed.