Y-shaped second Padma Bridge and four-lane roads could transform Pabna's communications
Travelling from the capital Dhaka to Pabna now requires a long detour via the Jamuna Bridge. Because of congestion and pressure around ferries and the bridge, the journey often takes five to seven hours. That picture could change significantly if a Y-shaped second Padma Bridge is built over the Padma River on the Paturia-Goalanda-Pabna connection and important roads in Pabna town are upgraded to four lanes.
Under the plan, travel time between Dhaka and Pabna could fall to two to two and a half hours once the new bridge opens. A BSS report said the proposed infrastructure would create a junction midway across the Padma from Paturia in Manikganj, with one branch of the bridge joining Goalanda in Rajbari and the other joining the Kazirhat or Nagarbari end in Pabna. That would create a new direct road link between the capital and Pabna.
Alongside it, a development proposal worth about Tk 4,000 crore to Tk 9,000 crore has come forward to widen Pabna town's internal roads and connecting highways. A feasibility study for the second Padma Bridge has gained importance in the government's road communications development plan, and upgrading several roads to four lanes to ease congestion in Pabna town and improve regional communications is also under discussion.
However, the Y-shaped design of the second Padma Bridge has not yet been finalised. The government's initial plan is considering linking Manikganj, Rajbari and Pabna, and a feasibility study is under way for that purpose. The bridge's final location, length, design and construction cost will be determined on the basis of the study results.
According to government information, building a second Padma Bridge at the Paturia-Daulatdia location is included in the election manifesto, and the corridor has also been considered in the Bangladesh Bridge Authority's master plan. Tk 4.50 crore has been allocated for the feasibility study in the 2026-27 fiscal year. However, neither the final project cost nor the construction financing has yet been determined.
Bridge Division Secretary Mohammad Abdur Rouf said the construction of a second Padma Bridge on the Paturia-Daulatdia corridor has gained importance in the government's development plan. A detailed feasibility study is needed before building such large infrastructure. A decision will be taken considering the river's behaviour, water flow, navigability, river training, bridge design, construction cost and economic usefulness. The Y-shaped bridge proposal must also be evaluated from technical and economic perspectives, and the final location, design and implementation plan can be determined only on the basis of the study results, he said.
Alongside the second Padma Bridge, three important roads have been proposed for four-lane upgrading to improve communications inside Pabna town. The proposal has come forward at the initiative of Pabna-5 MP Advocate Shamsur Rahman Shimul Biswas. Under the proposal, about seven kilometres of town roads will be widened in three phases.
In the first phase, the road from Chakchatiani Mosque via Chakchatiani graveyard to the Pabna-Ishwardi highway in front of Baliahalat Model Mosque is to be upgraded to four lanes. In the second phase, the road from Chandmari Mor via Pailanpur Mor to Power House Mor will be widened. In the third phase, the road from the central bus terminal via Mujahid Club, Ananta Cinema Hall and Abdul Hamid Road to Gachpara Mor has been proposed for four-lane upgrading.
MP Advocate Shamsur Rahman Shimul Biswas said Pabna has long faced various problems in communications infrastructure. Travelling from Dhaka to Pabna requires a long detour via the Jamuna Bridge, costing both time and money. He said they want direct communications between Pabna and the capital through a second Padma Bridge over the Padma. There is a proposal for one branch of a Y-shaped bridge from Paturia to join Goalanda and the other branch to join Pabna's Kazirhat or Nagarbari. Alongside that, an initiative has been taken to upgrade three important town roads to four lanes. If these plans are implemented, Pabna's communications system will see a revolutionary change, he commented.
Pabna is an important district of the north-western region in agriculture, industry and trade. A huge number of vehicles move every day around the Ishwardi EPZ, the Rooppur Nuclear Power Plant, sugar mills, agriculture-based industrial establishments and various commercial centres. Improved road communications are needed to transport agricultural and industrial products produced in Ishwardi, Sujanagar, Santhia, Bera, Chatmohar and Bhangura.
If the second Padma Bridge is built, direct communications could open between Pabna and both Manikganj and Rajbari. That could create new opportunities not only for travel to Dhaka but also for goods transport with various districts of the south-western region. If agricultural products, fish, dairy products and factory goods can be marketed quickly, transport costs and time could fall while trade expands. Direct road communications replacing river-dependent travel from the Bera and Kazirhat areas could also have a positive effect on the local economy. New communications opportunities could open for people in Rajbari, Manikganj, Natore and Sirajganj as well, and travel from Ishwardi, Chatmohar, Sujanagar, Santhia and other Pabna upazilas to the capital and regional commercial centres could become easier.
Md Forkan Reza Biswas Badsha, president of the Pabna Chamber of Commerce and Industry (PCCI), said Pabna is a highly promising district in agriculture, industry and trade, but limitations in the communications system often mean extra time and money are spent transporting goods. Transport cost is a major issue in sending agricultural and industrial products to Dhaka and other large markets in the country. He said businesspeople would benefit if the second Padma Bridge is built and important town roads are upgraded to four lanes: goods transport time would fall, opportunities to establish new industrial enterprises would be created and local employment would increase. He demanded effective steps for quick implementation of the projects.
Those concerned say improving Pabna's communications is not only about travel convenience for one district's people, but also an important opportunity to strengthen economic links between the northern and south-western regions. However, ensuring transparency, securing financing and finishing work on time at every step from announcement to implementation will be the biggest challenge.