Zoo Modernisation Master Plan Stuck for Four and a Half Years; Tk 333 Crore First-Phase Project Sent to Planning Commission

A master plan drawn up four and a half years ago to modernise the country's zoos has still not been implemented and remains confined to discussion. The Department of Livestock Services says the government is now considering implementing the master plan step by step through smaller projects rather than one large project.
In the first phase, the Ministry of Fisheries and Livestock has sent a Tk 333 crore project proposal to the Planning Commission to modernise the Bangladesh National Zoo at Mirpur in the capital and the Rangpur Zoo.
The master plan was prepared by the ministry over four years, from 2018 to 2021, at a cost of Tk 34 crore. It was drawn up by the Singapore-based company Bernard Harrison and Friends and the Bangladeshi firm Desh Upadesh. Implementing it would cost an estimated Tk 1,500 crore.
The master plan envisages keeping the National Zoo's animals in cage-free environments. Across about 77 hectares there would be room for 223 species — 102 native species, 66 tropical species, 40 African species and 15 nocturnal species, plus another 10 species in a children's active zone — in a total of five habitats.
Some 17.68 hectares have been allocated for a 'Bangladesh Habitat' zone, to be modelled on the mangrove forest of the Sundarbans. Animal enclosures would be set among wetlands, housing 26 species of fish, 9 species of reptile, 54 species of bird and 12 species of mammal. The plan also includes five new walking paths, two tram routes and two boat routes.
During the previous government's tenure, project proposals (DPPs) were prepared several times to implement the master plan, but no project was ever taken up.
A source linked to the zoo said the current government initially considered implementing the master plan in the first phase through a public-private partnership (PPP). However, the planning wing of the Department of Livestock Services says a proposal titled 'National Zoo and Rangpur Zoo Modernisation Project (Phase One)' has been submitted to the Planning Commission, is awaiting a PEC meeting and is included in the commission's green pages. Of the Tk 333 crore, Tk 186 crore would be spent on Rangpur Zoo and the rest on the National Zoo.
Department director Dr Mohammad Bazlur Rahman said that although the master plan called for five habitats, the proposed project would build one habitat, named 'Bangladesh'. On 18 hectares on the zoo's northern side, it would house 102 native species in 21 sheds in a natural environment. Rangpur Zoo would see mostly infrastructure development. The five-year project could begin next January.
Zoo experts, however, say that even if projects large and small are implemented, no positive change will come unless wildlife specialists are involved in zoo management. Wildlife specialist Dr Muhammad Ali Reza Khan, who was a consultant in preparing the master plan, expressed doubt about how the department would implement it without minimum experience.
Meanwhile, 10 animals at the National Zoo are being kept without companions in violation of the law: a rhinoceros, a spotted hyena, a striped hyena, a kangaroo, an Indian sarus crane, a gibbon, a Kulu monkey, an African white lion, a hamadryas baboon and a cassowary. Some have been alone for nearly a decade and a half. Under the Zoo Act 2023, no animal may be kept alone, separated from its group or natural environment, without the written or specific instruction of a veterinary officer.
National Zoo director Dr Md Shahinur Alam said the government has approved a list of animals to be purchased for the zoo, which includes bringing companions for the solitary animals. There is a plan to buy a hyena and a gibbon in the current 2026-27 fiscal year.
Director General of the Department of Livestock Services Md Shahzaman Khan said the government plans to implement the master plan step by step. In the first phase, Rangpur Zoo's infrastructure will be developed and the National Zoo's 'Bangladesh part' will be built. Once the master plan is implemented, visitors will find a fresh touch at the zoos.