Rooppur Unit 1 Disconnected from Grid After Peaking at 375 MW in First Test Phase, Second Phase in Preparation
The first unit of the Rooppur Nuclear Power Plant produced a maximum of 375 megawatts in the first phase of trial power supply to the national grid. After supplying power for about eight and a half hours, the unit was disconnected from the grid on Tuesday night. Preparations for the second phase of testing are now under way.
The unit was disconnected from the grid at 11:50pm on Tuesday (17 November). The authorities said power supply has been suspended temporarily as part of preparations for the next technical tests.
Dr Jahedul Hasan, managing director of the Nuclear Power Plant Company Bangladesh Limited (NPCBL), confirmed the matter. He said that after a break of about 28 hours, there is a plan to supply power to the national grid again for four to six hours in the second phase.
Earlier, Rooppur's power was connected to the national grid for the first time at 3:16pm on Tuesday. Twenty-nine minutes after the connection, production reached 350 megawatts.
Considering the stability of the grid, production was then kept at 300 megawatts. It was gradually raised to a maximum of 375 megawatts.
The activity began in the presence of Science and Technology Minister Fakir Mahbub Anam. Concerned officials said that before supplying power to the grid, the compatibility of the generator and the national grid's voltage, frequency and other electrical characteristics was ensured. Power supply then began in coordination with the grid.
People involved in the project said the next tests will verify the capability of the turbine, generator, control system and integrated operation with the national grid.
If the results of these tests are satisfactory, trial operation will begin with the approval of the Bangladesh Atomic Energy Regulatory Authority. At this stage, production will be raised step by step and the performance of the plant's various systems will be tested.
Under the contract with the Russian contractor Rosatom, there is a plan for commercial power supply at full capacity from the first unit after 10 months of trial operation. This period will be counted from the day trial operation begins after the regulator's approval.
The science and technology minister has said the target is to raise the first unit's production to 1,100 to 1,200 megawatts by next January. However, raising production will depend on the test results and the regulatory authority's approval.
Russia's Atomstroyexport is building two units of 1,200 megawatts each at Rooppur. Once both units are operational, the plant's total production capacity will stand at 2,400 megawatts.