Japanese consortium to run Shahjalal's third terminal, Bangladesh to get 27 percent of revenue, passenger fee to be Tk 1,559

A Japanese consortium is set to take responsibility for operating and maintaining the third terminal of Hazrat Shahjalal International Airport. It is going to sign a 15-year lease (concession) agreement with Bangladesh for this purpose.
Passengers using this terminal will have to pay an embarkation fee of 12.50 dollars, which is 1,559 taka in Bangladeshi currency. The fee is currently 500 taka. The government charge taken from a passenger for using the airport when travelling abroad is called the embarkation fee.
Bangladesh will receive 27 percent of the revenue earned from passenger transport, or 2.1 dollars per passenger. For cargo transport, Bangladesh will receive 27 percent of the income per tonne, or 11.5 dollars.
A proposal to sign such an agreement was approved in principle on Monday at a meeting of the cabinet committee on economic affairs at the Secretariat, chaired by Finance and Planning Minister Amir Khasru Mahmud Chowdhury. The Finance Ministry announced the approval after the meeting.
The information presented at the meeting by the Civil Aviation and Tourism Ministry did not name the group formed by the Japanese companies. But ministry sources said those who built the terminal will also operate it.
A responsible Finance Ministry source said the meeting was told that a Japanese company had expressed interest and submitted a financial proposal for post-construction operation and maintenance of Terminal-3. The operation and maintenance work will be done by the Japanese Sub-Working Group (SWG). Invest Bangladesh has scrutinised the SWG proposal and completed negotiations.
Under the terms of the agreement, the Japanese company will pay Bangladesh a one-time advance of 81 lakh dollars (about 100 crore taka) over the 15-year term. Biman Bangladesh Airlines will provide up to 50 percent of ground handling services for international airlines.
The Hazrat Shahjalal International Airport expansion project was approved in 2016 and work began in 2019. The work went to a consortium of four Japanese companies from the airport operation, infrastructure development, engineering and investment sectors. The consortium includes Japan Airport Terminal Company, Sumitomo Corporation, Nippon Koei and Narita International Airport Corporation. The project cost is estimated at 22,213 crore taka, and its term ends on 30 June 2027.
The third terminal is built over 542,000 square metres, with a floor space of 230,000 square metres. Once it opens, annual passenger capacity will rise from 8 million to 24 million. It has 26 boarding bridges, 115 check-in counters, 66 departure, 59 arrival and 3 VIP immigration desks. It is connected to the metro rail, the elevated expressway and the Hajj camp.
The project taken up for operating and maintaining the third terminal is a separate project. It was taken up during the Awami League government on a public-private partnership (PPP) basis. Its implementing agency is the Civil Aviation Authority of Bangladesh (CAAB). The 210 crore US dollar project, aimed at ensuring terminal operation, passenger service, baggage management, ground handling and cargo handling, received approval in principle on 19 January 2023. The agreement is due to be signed by 30 November.
Civil Aviation and Tourism Minister M Rashiduzzaman Millat told reporters at the Secretariat on Monday that preparations to inaugurate the third terminal are under way. The agreement with Japan will be signed by 30 November. After that, partial operations of the terminal will begin on 16 December with four flights. It will take another 14 months to become fully operational.
According to CAAB sources, 8.52 million passengers travelled through Hazrat Shahjalal International Airport in January-June 2026. Of them, 7.34 million were international passengers and 1.18 million were domestic passengers.