Eight Months After Work Order, Paving of Five-Kilometre Badarganj Road Yet to Begin

Staff Reporter
Eight Months After Work Order, Paving of Five-Kilometre Badarganj Road Yet to Begin
Photo: Collected

Paving work on the five-kilometre road from Mostafapur Ghat to Kalighat in Badarganj upazila of Rangpur has not begun even eight months after the work order was issued. Thousands of local people are suffering as they travel along the unpaved road.

Residents complain that only about three months remain before the contract period expires. With the work still not started, uncertainty has grown over whether the road will be finished within the scheduled time.

According to the upazila engineer's office, the government allocated Tk 3 crore 74 lakh 94 thousand 502 for paving the five-kilometre road from Mostafapur Ghat to Kalighat. The contract was awarded to Messrs Ranga Construction of Rangpur. The work order was issued on March 23, and under the contract the work is due to be completed by February 28, 2027.

Local people say there is no end to their suffering because of the road's long-standing poor condition. Even light rain turns the road into mud, and transport of agricultural produce almost comes to a halt because of the mud.

Asked about the delay, contractor Abdur Rob Ranga said, 'I was ill. I could not start the work for so long because I was abroad for treatment. But I will start the work soon.'

Badarganj Upazila Engineer Rabiul Islam said the work order has already been issued and the work is scheduled to end on February 28. He said inquiries would be made into why the contractor has not yet started, and necessary steps would be taken to begin the work quickly.