Five Months On, Dewanganj's Tk 2 Crore Project List Still Unpublished as PIO Claims Work '100 Percent Complete'

In Jamalpur's Dewanganj upazila, the deadline for rural infrastructure development projects worth nearly Tk 2 crore expired five months ago. The project implementation officer (PIO) claims the work has been implemented 100 percent, yet the list of the projects has still not been published. As a result, local residents cannot learn where, when and for how much money the work was done.
According to the district relief and rehabilitation officer's office, in the 2025-26 fiscal year the Department of Disaster Management allocated Tk 88 lakh to Dewanganj upazila under the Test Relief (TR) cash programme for rural infrastructure renovation and maintenance, from the quota of M Rashiduzzaman Millat, member of parliament for Jamalpur-1 (Dewanganj-Bakshiganj) and minister for civil aviation and tourism. A total of 53 projects were taken up with that money.
Under the Cash for Work (Kabita) programme, five projects were taken up with an allocation of Tk 30.25 lakh. Under the Food for Work (Kabikha) programme, 93 metric tons and 600 kg of rice and wheat were allocated; 12 projects were taken up under that programme and seven projects against Tk 46.75 lakh.
The projects were approved from the district in the first and second weeks of last June. Work was supposed to begin within 15 days of the district steering committee's approval and the allocation. The projects' deadline expired on June 30.
It has been alleged that because the project names, allocation amounts, implementation sites and the identities of the implementation committees' presidents, general secretaries and members have not been disclosed, local residents cannot obtain the information. There are also allegations that the project list was not provided even after applications were filed in the prescribed form under the Right to Information Act. PIO Mohammad Khabiruzzaman and Upazila Nirbahi Officer (UNO) Shah Juhurul Hossain have not published the list.
Under the work order, it was mandatory to put up a signboard at each project site before work began, stating the committee president's name and the allocation amount. It is alleged that the PIO did not comply. Field visits found no signboard carrying project information in the municipal town or in the villages of the unions. No project list is posted on the notice board of the PIO's office either, and there is no project-related information on the relevant website.
Local residents Sujan, Didar Mia, Bedena Begum and Habibur said that knowing information about government allocations is a citizen's right. But the PIO and the UNO are not publishing the project list, and residents cannot learn where work worth how much money was done.
A journalist, speaking on condition of anonymity, said: 'After repeatedly asking the PIO and the UNO for the project list and not getting it, I was forced to apply in the form under the Right to Information Act. But even a month after the application, they are not giving the project list.'
Mohammad Khabiruzzaman Khan, member-secretary of the upazila project implementation committee and PIO, said: 'The work of all the projects was implemented 100 percent before last June 30.' Asked why the list had not been published even five months after the deadline expired, he said: 'I am busy. We will talk later.'
Shah Juhurul Hossain, president of the upazila project implementation committee and UNO, said: 'I have received an application in the prescribed form seeking the project list. Publishing the project list is the PIO's responsibility. I have asked the PIO to supply the project list.'
Upazila BNP general secretary Abdur Rashid Sada said: 'I do not know about the project list not being published. Project information should be published.' Jahangir Selim, general secretary of the Jamalpur district corruption prevention committee, said: 'If information about government allocation projects is made public, there is accountability. Access to information is the people's right. Not supplying information in this case is an injustice.'
Muhammad Manik Mia, a local resident and a lawyer of the High Court Division of the Supreme Court, said: 'Not publishing the project list amounts to corruption. If a person is harassed while seeking information about government allocations, the victim can take legal recourse against the accused official.'
District relief and rehabilitation officer Md. Abdullahel Kafi said: 'There is a rule to put up signboards with all the project information at each project site. I will look into why the project list has not been published.' Mohammad Yusuf Ali, president of the project-approving district steering committee and deputy commissioner of Jamalpur, said: 'I do not know whether the project list has been published. The matter will be examined with importance.'