List of 77 projects worth nearly Tk 2 crore in Jamalpur's Dewanganj published five months after deadline

The list of rural infrastructure projects worth nearly Tk 2 crore in allocation in Dewanganj upazila of Jamalpur has finally been published — five months after the stipulated deadline expired. Following complaints of prolonged delay in disclosing the information, the upazila administration published the list on Thursday (November 26) afternoon.
The project list was uploaded at 1:50:24 pm on Thursday to the government website 'Bangladesh National Portal' used by the Project Implementation Officer (PIO).
According to sources at the office of the District Relief and Rehabilitation Officer (DRRO), as part of constituency-based allocations for rural infrastructure reform and maintenance in the 2025-26 fiscal year, money and food grains were allocated to Dewanganj upazila under various programmes from the allocation of Jamalpur-1 (Dewanganj-Bakshiganj) MP and Civil Aviation and Tourism Minister M Rashiduzzaman Millat.
Of this, Tk 88 lakh was allocated from the Department of Disaster Management under the Test Relief (TR) cash programme, against which 53 projects were taken up.
Under the Food-for-Work cash (Kabita) programme, five projects were taken against an allocation of Tk 30 lakh 25 thousand. Under the Food-for-Work (Kabikha) programme, 93 tonnes 600 kg of rice and wheat were allocated, covering 12 projects. In addition, seven more projects were taken against Tk 46 lakh 75 thousand.
The projects were approved at the district level in the first and second weeks of last June. Work was supposed to start within 15 days of the district steering committee's approval and allocation. As per the schedule, the projects' deadline expired on June 30.
Under the work order, it was mandatory to install a signboard at each project site before work began, naming the committee president and the allocation amount. But there are allegations that those concerned did not properly follow this instruction.
As no signboards with project information were installed and no detailed description was published on the website, local residents could not know in which areas work worth how much money had been done, or who was in charge of implementing the projects.
Even three and a half months after the projects' deadline expired, allegations arose that the upazila project implementation committee's member secretary and PIO Mohammad Khabiruzzaman Khan was not publishing the list. Later, some people applied in the prescribed information form to learn about the projects.
On October 16, a national daily's online edition published a report titled 'Nearly Tk 2 crore of projects in Dewanganj, foot-dragging over publishing the list'. Even after that, allegations arose that the list was not published although five months had passed since the deadline. Applicants complained that the list was not supplied even though the stipulated time passed after they applied for the information.
After another report titled 'Tk 2 crore of work implemented on paper, administration not giving the list' was published on November 25, activity was seen among those concerned. Finally, the project list was published on the website on Thursday.
District Relief and Rehabilitation Officer Md Abdullahel Kafi said the project list has already been published on the website. Asked why the list was published five months after the work deadline ended, he said the matter would be looked into.