Inani gas fire brought under control after 31 days as BAPEX succeeds in final operation at 9:30am

After a long 31 days, the natural gas fire that erupted from a deep tube well at Inani in Ukhiya, Cox's Bazar, has finally been brought under control. A specialist team from the Bangladesh Petroleum Exploration and Production Company Limited (BAPEX) controlled the blaze in a final operation at around 9:30am on Friday (November 27), ending a fire that had burned continuously for a month.
The main operation to control the fire had begun on Thursday (November 26) afternoon but was suspended in the evening because of failing light. A restart planned for 7am on Friday was delayed by a mechanical fault. After the fault was repaired, the necessary equipment installed and the casing and drilling pipes prepared, BAPEX specialists resumed the operation at around 9am — and within half an hour they had brought the fire under control.
BAPEX said the gas flames emerging through various points on the surface were stopped by installing a casing pipe 30 inches in diameter. A divert line connected to the casing redirected the gas flow along a fixed path, making the operation a success.
BAPEX specialists said a 55-member team, supervised by 20 officials, had worked for the past 14 to 15 days to control the fire, with preparation and technical work running for about 19 of every 24 hours. The biggest challenge of the whole operation was controlling the uncontrolled gas flow and the fire, and the country's own specialists and engineers succeeded using domestic technology.
The incident began on October 27, when gas suddenly erupted from underground during the installation of a deep tube well near the Chhoto Bridge area of Inani in Ukhiya upazila. At one point the escaping gas caught fire from an electric wire, and the fire then burned continuously for a month.
Under BAPEX's plan, the next step is to insert a drill pipe into the tube well and drill down to a depth of one thousand feet. During drilling, a special mud-like fluid (drilling mud) will be used to keep the underground gas pressure in balance. The necessary technical process will then be completed and the path of uncontrolled gas emission permanently sealed with cement.
Once the gas pressure is controlled, BAPEX specialists will collect the necessary samples from the area. A geological survey and a seismic survey will also be carried out. Based on analysis and evaluation of the survey data, a later decision will be taken on gas exploration and drilling an exploration well there.
The month-long gas emission and fire have renewed interest in the possibility of natural gas reserves beneath Inani. However, how much gas is there, how deep its source lies and whether it is commercially extractable cannot be stated with certainty without detailed exploration and surveys.